KUWAIT
Firm lagging on new projects after delayed U.S. Embassy
The same Kuwaiti-based company that largely built the troubled U.S. Embassy in Baghdad has run into problems in construction of a Gabon embassy and a new U.S. consulate in Surabaya, Indonesia.
BY WARREN P. STROBEL
wstrobel@mcclatchydc.com
WASHINGTON -- A year after problems emerged in the construction of the new U.S. Embassy in Baghdad, another State Department post being built largely by the same Kuwaiti-based company is engulfed by delays, recriminations and an Inspector General's probe, according to U.S. officials.
The embassy building, in the central African nation of Gabon, was supposed to be finished by April 2009.
Instead, according to U.S. officials and to documents obtained by McClatchy, the $55 million complex is only 7 percent complete. Workers are still excavating the construction site in the Gabonese capital of Libreville, and early 2010 is the new target date for completion. State Department officials confirmed that the department's inspector general is actively examining the project, but declined to provide details.
Patrick Kennedy, the Under Secretary of State for Management, acknowledged serious problems with the facility.
''The department is always concerned about timely and efficient progress on all our construction contracts, and we are working with the contractor to correct deficiencies,'' Kennedy said in a telephone interview.
The Gabon embassy and another project, a new U.S. consulate in Surabaya, Indonesia, have been ''plagued with problems'' that the State Department is working to remedy, said Joe Toussaint, a senior official in the department's bureau of Overseas Building Operations.
While it is neither so large nor strategic as the Baghdad embassy, the post in Gabon is high on the State Department's list for replacement under a 7-year-old program to move U.S. diplomats to secure, modern facilities worldwide.
It also illustrates how problems that emerged during the tenure of former State Department buildings chief retired Army Maj. Gen. Charles Williams, who resigned late last year after a congressional outcry over the Baghdad embassy, are still being wrestled with.
State Department officials point out that the worldwide embassy replacement program, which could total $17.5 billion when completed, has produced 64 new facilities since 2001, the majority without significant problems.
The embassy in Gabon is being built under a State Department contract with Aurora LLC, based in Rockville, Md.
According to officials and documents, however, the majority of the construction -- almost everything but the embassy's classified spaces -- is being handled by Kuwait-based First Kuwaiti General Trading & Contracting Co.
First Kuwaiti built the new Baghdad embassy, the largest U.S. diplomatic post in the world. The project was plagued by delays, allegations of procurement irregularities and a fire safety system that was certified as operational even though it didn't work properly. Two State Department audits of that project are under way.
State Department officials and others involved in the projects say that the Indonesia consulate is also troubled. It is 35 percent complete and will be at least five months late. In one case, according to a nongovernment source with direct knowledge, classified drawings depicting the consulate's secure areas were compromised.
But the problems in Gabon are said to be worse.
Those involved with the project, some speaking on condition of anonymity to avoid retribution, say First Kuwaiti has been slow to disburse funds needed to procure materials, and has had trouble recruiting local laborers to build the embassy. Workers brought in from neighboring Cameroon were recently sent back because they didn't have the proper work permits.
There's been near-constant turnover of senior managers overseeing the construction, those familiar with the project said.
An August study of the global embassy construction program by the State Department's inspector general reported that in Gabon, the ``contractor, on site 11 months, had been unable to complete temporary facilities and was struggling through the rainy season.''
First Kuwaiti didn't respond to a set of e-mailed questions about the project. Paul Jureidini, Aurora's general manager, said Monday that the project is getting back on track. ''We are turning things around, as far as I'm concerned,'' Jureidini said, adding that the project was already a year behind schedule when the company that won the original contract, Grunley-Walsh LLC, was sold and renamed Aurora.
Join the discussion
Note: If this is your first time using our NEW commenting system, you will have to LOG OUT and then LOG BACK IN.
The Miami Herald is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. In order to post comments, you must be a registered user of MiamiHerald.com. Your username will show along with the comments you post. Thank you for taking the time to offer your thoughts.
More World
World
- U.N. Security Council approves call for Gaza cease-fire
- U.S. ambassador says Britain is in Guantánamo talks
- Israel resumes Gaza campaign after pause for aid
- Cambodia prepares to try aging Khmer Rouge leaders
- Handlers on phone ordered Mumbai gunmen to kill hostages
- Latin American leaders slam Israel over Gaza
Videos
















My Yahoo
@Nyx.CommentBody@